University
of Michigan Medical Science Building
Mr.
James Aston,
I wanted to drop you a line to inform you how pleased
I am with how well this project went. This was a large
concrete demolition job with many obstacles that could
have hindered the progress of the overall project.
Due to the area you were working in you had to deal
with daily time constraints, noise and vibration problems,
access in and out of the building, and the biggest
problem of getting the debris out of the building.
These problems and more all made this a very difficult
job. Removing the 6 inches of concrete ceiling, approximately
4,500 sq. ft., was especially challenging. Add that
to the 7,500 sq. ft. of 8 inch thick concrete floor
made this project extremely hard. Your people did
an excellent job and finished a week early which made
everyone connected with the project here at the U.
of M. pleased. Your men performed very professionally
and should be commended. I have worked with your company
in the past and I felt confident going into this project
that you could handle a job of this size. I'm sure
I will be using you in the future.
Senior
Project Manager,
Rockey C. Bennett
University of Michigan
|
Project-Removing
1.2 million lbs. of concrete from operating hospital without
disturbing normal hospital activities.
- The
project required removal of 4,500 square feet of 5-inch
concrete ceiling and 7,600 square feet of 6-10-inch concrete
floor.
-
Even though the concrete floor being removed was on grade,
removing it required using a freight elevator to move the
material to the closest loading dock.
The University of Michigan Health Center
is a extraordinarily busy place. The complex consists of nearly
five million square feet of buildings. The complex includes
three separate hospitals (C.S. Mott Children's Hospital, University
Hospital and Women's Hospital). Over 17,800 people are employed
by the University of Michigan Health
System. Typical activity over the course of a year includes:
-
43,000 admissions
-
60,000 surgeries
-
1,500,000 clinic visits
-
72,000 urgent care visits
-
3,800 deliveries of new babies
While
Rockey Bennett from Construction Services wanted the 1.2 million
lbs. of concrete removed, it was made clear to Ohio Concrete
personnel that ongoing hospital activity took priority over
the demolition work. To minimize the impact on hospital activity,
Ohio Concrete made a decision to use electric concrete saws,
fork trucks and an excavator. The use of electric equipment
eliminated any fumes normally associated with gasoline or
diesel powered concrete saws. All construction activity had
to occur between 7:30 a.m. and 5:00 p.m. Sawing activity was
restricted to six hours a day between the hours of 9:00 a.m.
and 3:00 p.m. Crews had to cooperate with hospital personnel
when using a freight elevator when transporting the concrete
to the closest loading dock. It quickly became apparent it
was not practical to try to use the elevator between the hours
of 11:00 a.m. and 1:00 p.m.
REMOVAL
OF 4,500 SQUARE FEET OF 5-INCH CONCRETE CEILING
Over the past few years Ohio Concrete Sawing
and Drilling has purchased several electric powered fork trucks
and excavators in an effort to remove concrete from the inside
of buildings in the safest and most efficient manner. When
Ohio Concrete's operators removed a concrete ceiling at the University
of Michigan, they used a small electric fork truck to support
the ceiling while sawing and cutting into 3 x 7-foot pieces
of ceiling weighing about 1,000 lbs.
Ohio Concrete attached a wall saw to scaffolding
allowing their operators to cut the ceiling upside down from
below. The scaffold was locked into place using jack screws
to insure the
wall saw was secure during the sawing operation. Attaching
the wall saw to the scaffold allowed the operators to saw
the 4,500 square feet of ceiling from below without exhausting
their operators. Sawing the ceiling while it was supported
in this manner was the fastest and safest way of removing
the ceiling. The hydraulic wall saw was powered by a 40HP
electric hydraulic power source. It would have been impossible
to do any of the work from above the ceiling because of the
congestion. The area was very congested with steam lines,
water and sewer lines, electric conduit and piping for oxygen.
Attempting
to break the concrete from below would have been very dangerous
to the construction personnel and surely would have damaged
some of the utilities resting on the concrete being removed.
Also, breaking the concrete would have created far more noise
and dust than the sawing did.
After the concrete ceiling was cut and lowered
to the floor, the pieces were then moved to the elevator and
taken to the dumpsters for disposal. The University of Michigan
takes the concrete to a crushing facility and always makes
an effort to recycle their building materials.
REMOVAL
OF 7,600-SQUARE-FEET OF 6-10 INCH THICK CONCRETE FLOOR
Prior to removing any of the floor, Ohio
Concrete personnel finished the sawing and removal of the
ceiling. This gave them a solid surface for operators to operate
the fork trucks
and walk ons. The floor was cut using a 40HP electric concrete
saw. The entire area was cut into 4 x 4-foot squares. Removal
of the floor was done using electric fork trucks and a mini
electric excavator. Normally crews would have used their fork
trucks to remove this concrete, but discovered the mini excavator
was faster. The excavator was faster because it did not require
the use of any anchors normally used when removing concrete
with a fork truck. The excavator also had more leverage when
lifting pieces that contained abandoned plumbing lines, electrical
conduit and reinforcing at the bottom of the floor slab.
REASONS
FOR SUCCESS OF JOB
This job was very successful not only because
it was completed on time, it was also done with minimal disruption
to hospital activities. The tools used created no fumes, no
vibration
and very little noise. Employees working one floor away were
unaware that crews were removing over one million lbs. of
concrete from the floor below.
Ohio Concrete has been in business for 25-years.
Skip Aston, who started the company in 1981, is chairman of
the safety committee for CSDA. During the busy season Ohio
Concrete completes approximately 2,000 jobs a month in Ohio
and surrounding states. Ohio Concrete focuses their efforts
on service work. Many of their trucks are equipped with generators
powered through a PTO. These generators allow them to use
40HP electric saws very easily without having to connect to
480-Volt power in the building where they are working.
|