University of Michigan Medical Science Building

Mr. James Aston,

I wanted to drop you a line to inform you how pleased I am with how well this project went. This was a large concrete demolition job with many obstacles that could have hindered the progress of the overall project. Due to the area you were working in you had to deal with daily time constraints, noise and vibration problems, access in and out of the building, and the biggest problem of getting the debris out of the building. These problems and more all made this a very difficult job. Removing the 6 inches of concrete ceiling, approximately 4,500 sq. ft., was especially challenging. Add that to the 7,500 sq. ft. of 8 inch thick concrete floor made this project extremely hard. Your people did an excellent job and finished a week early which made everyone connected with the project here at the U. of M. pleased. Your men performed very professionally and should be commended. I have worked with your company in the past and I felt confident going into this project that you could handle a job of this size. I'm sure I will be using you in the future.

Senior Project Manager,
Rockey C. Bennett
University of Michigan

Project-Removing 1.2 million lbs. of concrete from operating hospital without disturbing normal hospital activities.

  • The project required removal of 4,500 square feet of 5-inch concrete ceiling and 7,600 square feet of 6-10-inch concrete floor.
  • Even though the concrete floor being removed was on grade, removing it required using a freight elevator to move the material to the closest loading dock.

The University of Michigan Health Center is a extraordinarily busy place. The complex consists of nearly five million square feet of buildings. The complex includes three separate hospitals (C.S. Mott Children's Hospital, University Hospital and Women's Hospital). Over 17,800 people are employed by the University of Michigan Health
System. Typical activity over the course of a year includes:

  • 43,000 admissions
  • 60,000 surgeries
  • 1,500,000 clinic visits
  • 72,000 urgent care visits
  • 3,800 deliveries of new babies

While Rockey Bennett from Construction Services wanted the 1.2 million lbs. of concrete removed, it was made clear to Ohio Concrete personnel that ongoing hospital activity took priority over the demolition work. To minimize the impact on hospital activity, Ohio Concrete made a decision to use electric concrete saws, fork trucks and an excavator. The use of electric equipment eliminated any fumes normally associated with gasoline or diesel powered concrete saws. All construction activity had to occur between 7:30 a.m. and 5:00 p.m. Sawing activity was restricted to six hours a day between the hours of 9:00 a.m. and 3:00 p.m. Crews had to cooperate with hospital personnel when using a freight elevator when transporting the concrete to the closest loading dock. It quickly became apparent it was not practical to try to use the elevator between the hours of 11:00 a.m. and 1:00 p.m.

REMOVAL OF 4,500 SQUARE FEET OF 5-INCH CONCRETE CEILING

Over the past few years Ohio Concrete Sawing and Drilling has purchased several electric powered fork trucks and excavators in an effort to remove concrete from the inside of buildings in the safest and most efficient manner. When Ohio Concrete's operators removed a concrete ceiling at the University of Michigan, they used a small electric fork truck to support the ceiling while sawing and cutting into 3 x 7-foot pieces of ceiling weighing about 1,000 lbs.

Ohio Concrete attached a wall saw to scaffolding allowing their operators to cut the ceiling upside down from below. The scaffold was locked into place using jack screws to insure the wall saw was secure during the sawing operation. Attaching the wall saw to the scaffold allowed the operators to saw the 4,500 square feet of ceiling from below without exhausting their operators. Sawing the ceiling while it was supported in this manner was the fastest and safest way of removing the ceiling. The hydraulic wall saw was powered by a 40HP electric hydraulic power source. It would have been impossible to do any of the work from above the ceiling because of the congestion. The area was very congested with steam lines, water and sewer lines, electric conduit and piping for oxygen. Attempting
to break the concrete from below would have been very dangerous to the construction personnel and surely would have damaged some of the utilities resting on the concrete being removed. Also, breaking the concrete would have created far more noise and dust than the sawing did.

After the concrete ceiling was cut and lowered to the floor, the pieces were then moved to the elevator and taken to the dumpsters for disposal. The University of Michigan takes the concrete to a crushing facility and always makes an effort to recycle their building materials.

REMOVAL OF 7,600-SQUARE-FEET OF 6-10 INCH THICK CONCRETE FLOOR

Prior to removing any of the floor, Ohio Concrete personnel finished the sawing and removal of the ceiling. This gave them a solid surface for operators to operate the fork trucks and walk ons. The floor was cut using a 40HP electric concrete saw. The entire area was cut into 4 x 4-foot squares. Removal of the floor was done using electric fork trucks and a mini electric excavator. Normally crews would have used their fork trucks to remove this concrete, but discovered the mini excavator was faster. The excavator was faster because it did not require the use of any anchors normally used when removing concrete with a fork truck. The excavator also had more leverage when lifting pieces that contained abandoned plumbing lines, electrical conduit and reinforcing at the bottom of the floor slab.

REASONS FOR SUCCESS OF JOB

This job was very successful not only because it was completed on time, it was also done with minimal disruption to hospital activities. The tools used created no fumes, no vibration and very little noise. Employees working one floor away were unaware that crews were removing over one million lbs. of concrete from the floor below.

Ohio Concrete has been in business for 25-years. Skip Aston, who started the company in 1981, is chairman of the safety committee for CSDA. During the busy season Ohio Concrete completes approximately 2,000 jobs a month in Ohio and surrounding states. Ohio Concrete focuses their efforts on service work. Many of their trucks are equipped with generators powered through a PTO. These generators allow them to use 40HP electric saws very easily without having to connect to 480-Volt power in the building where they are working.

Recent Jobs

Free World Concrete Registration

 
 


 
 


Home | Services | Estimates | Faq’s | Job Opportunities | Contact Us | Training / Safety Video

Akron, OH (330) 633-5104 | Ann Arbor, MI (734) 996-9505 | Cincinnati, OH (513) 723-0099
Columbus, OH (614) 252-1122 | Dayton, OH (937) 746- 8999 | Jackson, MI (517) 782-1202
Redford, MI (734) 525-5915 |
Toledo, OH (419) 841-1330

Toledo Ohio Web Site Design By Webcasters.com
Copyright 2007 Ohio Concrete & Ohio Media, Inc.
Toledo Ohio Web Site Hosting By Webcasters.com